Open reference · METI FIT disclosure
Japan’s small-scale biomass projects, mapped.
日本の小規模バイオマス発電マップ(2MW以下)
This is an open, citable reference to woody biomass Japan projects and all other small-scale biomass at 2 MW and below, drawn from METI’s monthly FIT certification disclosure; this snapshot is 2026-05. A plant is shown as operating once it files an operation-start report, and as certified-but-not-operating when it holds FIT certification without one. Projects certified four or more years ago with no reported operation start are shown as stalled — many will never be built without a new developer.
Operating · 稼働中Certified (<4 yrs) · 認定済(4年未満) Certified 4+ yrs, not operating · 認定から4年以上・未稼働Locations shown at district (大字) level.
用語:事業計画認定情報(FIT certification disclosure)・運転開始報告年月(operation-start report)・認定未稼働(certified, not operating)・木質バイオマス(woody biomass)・大字(district)
Where the stalled projects sit
The 10 prefectures holding the most stalled capacity — projects certified 4+ years ago (認定未稼働) with no reported operation start.
| Prefecture | Stalled (4y+) | Certified (<4y) | Operating | Total kW |
|---|---|---|---|---|
| Mie 三重県 | 7 | 33 | 13 | 20,461 |
| Gunma 群馬県 | 7 | 3 | 13 | 17,504 |
| Miyazaki 宮崎県 | 6 | 1 | 7 | 10,551 |
| Shizuoka 静岡県 | 5 | 3 | 17 | 21,473 |
| Kagoshima 鹿児島県 | 4 | 19 | 28 | 15,232 |
| Hyogo 兵庫県 | 4 | 2 | 15 | 17,869 |
| Niigata 新潟県 | 3 | 6 | 12 | 15,921 |
| Ibaraki 茨城県 | 3 | 0 | 10 | 14,913 |
| Hokkaido 北海道 | 2 | 14 | 123 | 53,844 |
| Akita 秋田県 | 2 | 3 | 15 | 11,150 |
Hold or founded a certified project that never reached operation? That is exactly the situation Analema develops.